Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • Notice
    • Vigilance Awareness
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
    • RISK ASSESSMENT & MANAGEMENT POLICY
    • WHISTLE BLOWER POLICY
    • CORPORATE SOCIAL RESPONSIBILITY POLICY
Flash News
MMRC

Flash News

'Station Semi-Naming & Branding Rights at Mumbai Metro Line 3 (Stage-2)' RFP
Supplying consumable materials and maintenance of Electrical installations at Transit Office building of MMRCL at BKC, Bandra (E) in Mumbai for 2 years (2023- 2025)
Supplying consumable materials and maintenance of Electrical installations at Transit Office building of MMRCL at BKC, Bandra (E) in Mumbai for 2 years (2023- 2025)
'Station Semi-Naming & Branding Rights at Mumbai Metro Line 3 (Stage-2)' RFP
‘Appointment of Transaction Advisor for disposal of plot at Nariman Point for Metro Line 3’
Supplying consumable materials and maintenance of Electrical installations at Transit Office building of MMRCL at BKC, Bandra (E) in Mumbai for 2 years (2023- 2025)
Providing of motorized rolling shutters at Aarey colony car depot of Mumbai Metro Line ‐3 project
DISASTER CONTROL ROOM NUMBER - 8779177592
'Station Semi-Naming & Branding Rights at Mumbai Metro Line 3 (Stage-2)' RFP
Supplying consumable materials and maintenance of Electrical installations at Transit Office building of MMRCL at BKC, Bandra (E) in Mumbai for 2 years (2023- 2025)
  1. Home
  2. Project
  3. Project Timeline

Project Timeline

MMRC
Project Timeline
 

Concept of Metro, proposed for the first time in Mumbai

1969
 

Reflected in Development Plan

1991
 

Feasibility study carried out by MMPG

1997
 

Mumbai Metro Master Plan initiated by MMRDA

2003
 

Mumbai Master Plan prepared by DMRC

  • Length -146 km
  • Corridors –9
  • Phases –3 phases
2004
 

Public Consultation on Mumbai Metro Master Plan

2004
 

Metro Line –1 awarded on PPP

2006
 

Metro Line –2 awarded on PPP

2008
 

Line 3 preparatory works Initiated on PPP model; however, not found feasible on VGF model

2009
 

Project initiated for EPC model with JICA funding in 2011

2011
MMRC

Prospective Timeline

 

2011 - 2013

  • Publication of revised DPR for fully underground Colaba-Bandra-SEEPZ Corridor
  • Alignment publication of MML - 3
  • Submission of Proposal to Government of India
  • Occurrence of Pre-PIB
  • Approval of JICA loan
  • Approval of PIB & Cabinet
  • Signing of Loan agreement
  • Public consultation for SIA & EIA
  • Approval of Government of India
  • Notification under Metro Act
  • Signing of loan agreement between GoI & JICA
 

2013 - 2015

  • Approval of State Cabinet
  • Approval of Maharashtra Govt.
  • PQ contractors for civil works-Tunnels & Stations
  • Appointment of General Consultants
  • Publishing of Tenders for civil works-Tunnels & Stations
 

2015 - 2017

  • Tendering process of Civil Work & appointment of Contractor
  • Start of Civil Work (Tunnels & Stations)
  • Basic designs of System components
  • Issuance of Tenders for Systems/Rolling stock
  • Completion of Detailed design manufacturing & installation
 

2017 - 2024

  • Completion of Civil Work
  • Completion of P-way work
  • Completion of Testing & certification
  • Final Commissioning
MMRC
MMRC

Recent News

mmrc
महाराष्ट्र की पहली अंडरग्राउंड मेट्रो
+03 Aug 2023
हुतात्मा स्मारक मेट्रो स्थानक पूर्णत्वाकडे
+03 Aug 2023
मेट्रो-३ च्या हुतात्मा चौक स्थानकाला हेरिटेज वास्तूंचे कोंदण
+02 Aug 2023
मेट्रो 3 की बाकी चार गाड़ियां सितंबर और नवंबर में आएंगी
+02 Aug 2023
मेट्रो-३ च्या चार गाड्या दोन टप्प्यांत येणार
+01 Aug 2023
First pedestrian subway connecting CSMT with Metro-3 gets go-ahead
+24 Jul 2023
Previous Pause Next
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros